Teal Rd. Project in Lafayette

Teal Road Project Description:

The U.S. 52/Teal Road reconstruction project is approximately three miles in length.  The western end of the project will start just west of Old Romney Road on State Road 25 (locally known as West Teal), going east to Old U.S. 231, proceeding north on Old U.S. 231 to the 4th Street/ Poland Hill Road intersection, and continuing east on U.S. 52/Teal Road terminating between Brothers Drive and South 30th Street, all located in Lafayette.

The project will partially reconstruct Teal Road along with other improvements such as storm sewers and new or reconstructed sidewalks and curbs where necessary.  Also improved turning movements at the intersecting roadways at Old U.S. 231, Elston Road, Crestview Place, Edgelea Drive, and 26th Street along with improving the access and exit to Teal Road. The intersection of 4th Street/Poland Hill Road and U.S. 52 will be improved by removing the splitter islands, adjusting the alignment, and placement of a new storm sewer at the intersection.

2022 Calendar Year:

Earliest Date to Begin Work: April 1st, 2022

Projected Start Date: April 4th, 2022

Restriction Time for 9th & 18th St: 6/1/2022 – 8/1/2022 (60 Calendar Days)

2023 Calendar Year:

Restriction Time for 9th & 18th St: 6/1/2023 – 8/1/2023 (60 Calendar Days)

Closure Time for 4th St: 6/1/2023 – 8/1/2023 (60 Calendar Days)

Intermediate Completion Date for Planned Work: 9/30/2023

Construction Restrictions:

During the calendar year, full access shall be open and maintained for all sidewalks and curbs ramps at 9th St, 18th St, and 22nd St intersection with US 52 and no construction activities at these locations shall be performed between timespans listed below:

  • August 1, 2022 through June 1, 2023
  • August 1, 2023 through June 1, 2024

During the Tippecanoe County Fair, full access shall be open and maintained for all sidewalks and curbs ramps between the 9th St and 18th Str, on US 52 and no construction activities at these locations shall be performed between timespans listed below:

  • July 16, 2022 through July 23, 2022
  • July 15, 2023 through July 22, 2023