The City of Columbus is seeking a water rate increase and financing authority in a pending case before the Commission (Cause No. 46173). The OUCC and the utility have reached an agreement in principle and anticipate filing a formal settlement agreement by Apr. 30, 2025.

The IURC held a Mar. 10, 2025 public field hearing in Columbus. The OUCC issued a media release inviting public comments on Feb. 25, 2025.

A Commission order is expected later this year.

All publicly filed documents in the case, including the City's testimony, are available from the IURC's online case file for Cause No. 46173.

The IURC approved Columbus' current water rates in 2021.

Municipal sewer utilities are exempt from IURC oversight. Locally elected city and town councils approve their rates.